What do you need to know about the mandatory installation of charging infrastructure?
Text and images Titeca Pro Accountants & Experts

Mandatory charging points will also apply to existing buildings from 2025
In most cases, anyone who has applied for planning permission in recent years for a new-build project or a major renovation of an existing building has been required to provide charging infrastructure in the car park. Following the implementation of a European Directive, this requirement will be extended from 1 January 2025. Existing commercial buildings will also have to be fitted with charging infrastructure. What do business owners need to know? Tax adviser Victor Battiau explains the key points.
The requirement to provide charging infrastructure already applies to owners who have applied for planning permission for a new build or major renovation since 11 March 2021. The government wants to facilitate the transition to electric mobility in this way. In this article, Victor Battiau, tax expert at Titeca pro accountants & experts, sets out the key points to bear in mind.
Non-residential buildings
If the application concerns a non-residential building with more than 10 parking spaces, the owner must install at least two charging points as part of the major renovation. In addition, cabling (or at least cable trays) must be provided to allow charging points to be installed in future at one in every four parking spaces.
Residential buildings
The requirements for residential buildings go a step further. When a developer constructs a new residential building with more than two parking spaces, ducting must be provided for every parking space. This means that the charging point itself does not have to be installed straight away.
In practice, this means that when a house or flat with more than two parking spaces is built, ducting must be provided for the installation of one charging point per parking space. Garages also count as parking spaces, but a driveway is considered an access route. In other words, a new-build home with one garage and a driveway is not subject to the requirement.
For major renovations of existing residential complexes, the minimum threshold for mandatory installation rises to 10 parking spaces.
What is changing for existing buildings?
From 1 January 2025, existing non-residential buildings with more than 20 parking spaces will also be required to install at least 2 charging points. The requirement will apply whether or not a planning application is submitted. In practice, this means that every commercial building with a medium-sized or large car park will have to have at least 2 charging stations from 1 January 2025, even if no renovation work has recently taken place on the site.
Nothing is changing for existing residential buildings. Mandatory installation will apply only if the existing rules on major renovations are met.
Which car parks are covered?
Car parks are subject to the requirement if they are located inside a building or car park structure, or if they are adjacent to a building. Major renovations also trigger a requirement to provide charging infrastructure if the renovation work covers the car park or the electrical infrastructure of the building, car park structure or car park.
Anyone with questions about the requirement and the measures that need to be taken can make an appointment with our pro experts.
Een zakelijke vraag aan Titeca? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming business mobility
- SubjectHR, finance & IT
- CompanyTiteca