“Our construction partners did everything they could to meet the tight schedule”

Text Björn CrulImage Govar Industriebouw

Bert Catteeuw, voor de betonnen gevel met blauwe bol als herkenbaar inkomsas.
Bert Catteeuw, voor de betonnen gevel met blauwe bol als herkenbaar inkomsas.

New premises give Kaster room to keep growing

Work is nearing completion on the new business premises of Kaster Keukens at Krommebeek business park in Roeselare-Beveren. This young kitchen company urgently needed more space after a period of strong growth. Construction partners Govar Industriebouw, Afschrift and Intec pulled out all the stops to complete the new premises in less than a year. “We’re looking forward to moving into our state-of-the-art, sustainable building,” says managing director Bert Catteeuw enthusiastically.

Kaster Keukens’ story is a fine example of entrepreneurship. Five years ago, Bert Catteeuw decided to set up his own kitchen company, specialising in made-to-measure work. He started out with four employees and an automated production facility. Barely five years later, the team has grown to 46 employees, and its current premises on Populierstraat in Roeselare are bursting at the seams.

“I had experience in the kitchen sector and wanted to use my own company to fill a niche: made-to-measure kitchens, cabinets and interiors produced using a standardised, automated process,” Bert begins. “This combination allows us to offer customers the interiors of their dreams at a competitive price. And it has proved a success: the idea caught on, and we’re still amazed by how many people find their way to our showroom.”

At the beginning of November, Kaster launched a brand-new production line at Krommebeekpark.

Top quality and local customisation

Kaster Keukens works with both private clients and property developers delivering projects in East and West Flanders. “The split is roughly 50-50. It also helps us achieve production volumes and work efficiently. Around four projects come off the production line each day. We make kitchens, dressing rooms, hallway wardrobes, fireplace surrounds and more. There is a clear trend towards people choosing a single style for their interiors. We can meet that demand by combining top quality with local customisation,” says Bert Catteeuw.

The company’s success led the young entrepreneur to consider expanding two years ago. “Despite the coronavirus pandemic, the raw materials crisis and the war in Ukraine, we could see that our concept was working. We wanted to grow, while keeping the business manageable. That meant we needed a new factory with the capacity to produce up to eight projects a day. So we started looking for a site in the region where we could build new business premises.”

The new site was Krommebeekpark in Roeselare-Beveren. Kaster asked creative agency Maister, which had also developed its corporate identity, to shape the new building. “They opted for a concrete façade, with a blue sphere as a distinctive entrance,” Bert explains. “TIDES Architecten then took the design forward, handling the technical development, structural calculations and coordination.”

Bert was most impressed by Govar Industriebouw’s proposal, which combined steel and concrete construction.

No-nonsense approach

After a tender process, Govar Industriebouw emerged as the right contractor for the project, which has a floor area of 7,000 m² and a total usable area of 11,000 m² for the showroom, offices and production facilities. “Their proposal, combining steel and concrete construction, was the best. From our very first meeting, I also had a good feeling about Christophe Govaere’s approach: no-nonsense, taking charge and getting on with the job. That was important, because timing was crucial for us: we wanted to be operational at the new site within a year of breaking ground.”

The new building also features sustainable technologies. Bert Catteeuw says: “Everything is electric, and thanks to the solar panels on the roof, we’ll be able to operate almost energy-neutrally. We worked with Afschrift on everything related to electricity, and with Intec Group on plumbing and HVAC. Together with Govar Industriebouw, they proactively considered how to coordinate the planning and execution of the different works to meet the schedule. I also closely monitored the work myself, but the project management teams at all three construction partners certainly deserve credit.”

Thanks to the mild winter, this construction project by Govar proceeded very smoothly. “We’re now in the finishing stage. A brand-new production line started up at Krommebeekpark at the beginning of November. Production will then move over, and our offices and showroom should also be operational by early 2024. Thanks to the smooth cooperation with all our construction partners, we’ll have achieved our goal,” Bert concludes.

Een zakelijke vraag aan Govar? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeBuilding and using business premises
  • SubjectGeneral