Lamett makes a statement alongside the E17
Text Marlies DecavelImage Beeuwsaert Construct

Anyone driving along the E17 past Lamett’s site in Deerlijk is sure to take a look. The new building for the wood flooring specialist has an inviting appearance. Lamett teamed up with Beeuwsaert Construct from Ledegem to deliver the project. Both parties look back on the collaboration with satisfaction.
When Lamett bought its office building some fifteen years ago, there was enough space for a small showroom and offices for its ten employees. But the company grew quickly and the building became too small. The showroom moved to an external location in Waregem to make more office space available in Deerlijk. Lamett continued to grow, however, and now employs more than sixty people. The management therefore looked for a sustainable way to make the most of its site alongside the E17.

Optimal co-creation
From the outset, Lamett was involved in the design and layout of the redeveloped site. Operations director Sophie Stockman and finance manager Anja Engels drew on their experience at Lamett to create the ideal environment for customers and staff alike. Waregem-based architectural firm Wielfaert handled the design, while Beeuwsaert Construct ensured flawless execution.
“After demolishing the existing building, we started work on a new concept,” says Anja. “The ground floor comprises the loading and unloading areas and a storage warehouse. On the first floor, we created a beautiful, spacious showroom designed to immerse visitors in the brand. The second floor houses the offices at the rear and a welcoming meeting place for employees and customers, with views over the E17 and the surrounding countryside. The homely feel and warm, inviting atmosphere make a huge difference compared with before.”
A critical eye
Beeuwsaert Construct has extensive experience with projects of this kind. Working closely with the client and architect, the industrial construction specialist even amended the plans in a few places. “Our many years of expertise in industrial construction give us the confidence to question certain decisions, always in the client’s best interests,” explains Beeuwsaert project manager Jo Martens. “For example, the car park was not originally due to be resurfaced, even though it is an important part of the experience for suppliers and customers. We also made additional improvements to the loading bays to optimise workflow. That constructive critical approach results in a finished project where every element works perfectly.”

Operations continued throughout the works
As with any construction project, unexpected challenges can arise. In this case, the main obstacle for the contractors was the rainy weather. Jo says: “The hardest part came at the end. The building absolutely had to be finished before Flanders Flooring Days in early May. Unfortunately, we had to postpone the car park works three times because of the bad weather. In the end, despite the difficult conditions, we got everything ready on time. And that was after we had already had quite a puzzle to solve.”
Anja Engels agrees: “Beeuwsaert’s expertise and commitment are second to none. Jo was always there for us, ready with an answer or a tailored solution whenever we had a question. We had complete confidence that our new building was in good hands.” Jo Martens adds: “Believe it or not, Lamett remained operational throughout the works. Manoeuvring six-metre-high windows into place or carrying out electrical work while the company was running at full capacity? It was a major undertaking, but we are proud to have brought it to a successful conclusion.”
Have a business enquiry for Beeuwsaert Construct? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction
- CompanyBeeuwsaert Construct