Altez builds new tyre centre for family business Mortier
Text Anse KeisseImage Altez

A brand-new building for Banden Mortier has recently appeared along Ruiseleedsesteenweg in Tielt. The tyre centre decided to build entirely new premises at its familiar location, with spacious workshops, modern offices, a storage area and a private residence. The project was entrusted to Altez Construction Group, whose integrated approach shows that speed, quality and sustainability can go hand in hand.
The location of Mortier’s tyre centre, strategically positioned along a major thoroughfare, has always been a strong asset for the family business. Rather than move, the current generation decided to make a fresh start at its familiar site. With a complete new-build project, including two workshops, a storage area, offices and a private residence, Mortier opted decisively for modernisation and a future-focused approach to business.
Altez Construction Group handled the project, with its head office just 2 kilometres away. “Only the warehouse we built for them in 2016 was retained. The other buildings were completely demolished, and the functions were then brought together in one large, modern building,” says Arne Colpaert, sales manager at Altez, which completed the project to a tight schedule, fully tailored to Mortier’s day-to-day operations.

Robust and bright
The building rests on a cast-in-situ basement, which houses the technical installations and a water storage system that can also be used by the fire brigade if necessary. “The new building has a robust steel primary structure. Concrete columns and beams were used at strategic points to provide additional stability. All the steel and concrete used came from our own production facility,” Arne continues. This enables Altez to respond quickly without compromising on quality.
The warehouse façade was finished with low-wool grey concrete panels, while the front elevation was clad in render for a clean, contemporary look. “A central rooflight in the storage area and three large windows bring natural light into the workshop. This makes the working environment more pleasant and efficient,” Arne emphasises.
Minimal disruption, maximum efficiency
The result is an imposing complex with a mix of uses. “We divided the workshop into two sections: one for cars, the other for large vehicles such as lorries and agricultural vehicles. A further service that fits perfectly with Mortier’s customer-focused approach is the large space for storing winter tyres.” The building also contains a comfortable reception area where customers can wait or work while their tyres are changed, modern offices for staff and a luxurious flat on the upper floor, complete with a roof terrace.
One of the project’s biggest challenges was ensuring that Mortier could continue operating. “We carried out the work in phases so that the tyre centre could remain open,” says Colpaert. “The workshop was closed for only two days while the concrete floor was poured.”

A reliable construction partner
With this project, Altez, working closely with architectural practice Naert from Wingene, reaffirms its position as a reliable partner in commercial construction. “We are particularly proud of the result at Banden Mortier, a family business with a strong reputation,” Arne explains. “From the outset, we were able to align everything closely with expectations. Thanks to our in-house production and efficient site organisation, we were able to deliver the entire project, from demolition to finishing, smoothly and to a high standard. This project shows what is possible when craftsmanship, direct communication and mutual trust come together,” concludes Arne Colpaert of Altez Construction Group.
A business enquiry for ALTEZ? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeBusiness transfers and acquisitions
- SubjectConstruction
- CompanyALTEZ